NIGHT TUBE GATES

Supply and install Night Tube Gates at Various Stations
Year - 2017
Client – Tubelines Ltd.
Contact – Tim Young
Overall Value – £750,000

As part of the night tube preparation works, Tubelines had packages for various sizes and styles of gates. Initially we received 4 packages with a combined total of 34 gates at various stations, this was then extended through additional…

Project Details

MOORGATE NORTHERN LINE LINK WORKS

Construct lift shaft and escalator interface
Year - 2016
Client – BBMV/CROSSRAIL
Contact – Tony Goble (BBMV)
Overall Cost – £4,500,000

As part of the larger Crossrail project, the main contractor had a need for interface works between the existing station and 2 proposed new breakthroughs from the tunnelling works being undertaken to form 2 new pedestrian access routes to the…

Project Details

MOORGATE SHAFT ACCESS PLATFORMS

Supply and install tunnel access platforms within shaft
Year - 2015
Client – BBMV / Crossrail
Contact – Tony Goble
Overall Cost – £900,000

A 30m deep access shaft had been excavated by a previous Crossrail contractor to enable various tunnels to be excavated between Liverpool Street, Moorgate and two new East/West Crossrail running tunnels. An acceleration in the Crossrail…

Project Details

STRATFORD STATION ENTRANCES

Supply and install Night Tube Gates at Various Stations
Year - 2015
Client – JNG Construction / Tubelines Ltd.
Contact – Jay Olivant
Overall Cost – £750,000

Major works on Stratford Station have spanned multiple projects and disciplines. From the initial groundworks and civils to build the new platform 3a to four entrances to allow connections and increased capacity as well…

Project Details

WEMBLY PARK and HOUNSLOW EAST PLATFORM WORKS.

Replacement copers and tactile works and removal of RVAR
Year - 2013
Client – Tubelines Ltd.
Contact – Chris Hunt
Overall Cost – £300,000

At Wembley Park The removal of a 50m section of raised platform required that the entire surface be broken down 300mm in the structural slab, new sections of fast set concrete installed and a sacrificial surface applied to leave the…

Project Details

CHALFONT BANK STABILISATION

King Post and Plank Wall
Year - 2014
Client – UKDN/Track Partnership
Contact – Mark Lusher
Overall Cost – £700,000

The works involved the installation of a kingpost and plank wall to a 200m section of track in order to prevent further slippage over a particularly steep area. In excess of 400 300 x 300 UKBP of varying length but average 8 meter were driven over into position…

Project Details

ANNUAL TRACK DRAINAGE REMEDIATION

Rodding, pipe repair and CCTV at Various Stations
Year - Annual
Client – TfL / Lanes Group
Contact – Greg Hulbert
Overall Cost – approx. 800k

An annual workbank of cleaning and spot dig repairs have been succesfully delivered since 2010, the addition in 2015 of a dedicated CCTV division and Harben jetting unit has enabled us to supply the full package of reporting, planning…

Project Details

TOWER HILL - LIFT SHAFT A

Lift shaft construction from platform to street level
Year - 2015
Client – Cleshar / Balfour Beatty / Citizen M
Contact – Andy Chojnacki
Overall Cost – £650,000

The demolition of existing staircases, retaining walls and excavation of 300 tons of overburden to expose the ticket hall capping slab. Excavation of a lift pit at platform level and construction of a rising lift shaft…

Project Details

WEMBLEY CENTRAL STATION

New entrance Facade Cladding
Year - 2016
Client – SWIP / TfL
Contact – Ed Ruddick
Overall Cost – £250,000

Following on from the successful delivery of various station entrance designs and previous works, Spoor-tech could offer the confidence and proven track record for works of this nature.

The works involved the removal of the existing temporary entrance and the design…

Project Details

HAMMERSMITH CONTROL CENTRE

Demolition and Firestopping of Existing Structures within the Control Centre
Year - 2016
Client – SWIP
Overall Value – £160,000

TfL constructed a new control centre at Hammersmith to relocate control systems and staff to a brand new facility featuring state of the art safety and monitoring equipment. Towards the end of the project they had a change in scope that required modification…

Project Details